Please click on the link below to access the video footage of the Battery Energy Storage Bid Window 3 (BESIPPPP BW3) Bidders’ Conference that took place on Thursday, 9 May 2024.
ESIPPP Programme preliminary milestone dates, subject to change, are as follows:
Bidders' Conference - 4 (four) to 6 (six) weeks following the release of the RFP | |
Last date for Bidders to apply to Eskom for a Procurement Programme specific cost estimate letter (“CEL”) | 30 May 2024 |
Last date for Bidders to submit written questions in terms of clause 27.3 (Requests for clarification on the RFP and responses to requests) of this Part A - 30 (thirty) business days prior to the Bid Submission Date | 18 Sep 2024 |
Last date for compulsory Bid Registration, including payment of Bid Registration Fee (as per clause 11 (Compulsory Bid Registration) of this Part A) - 20 (twenty) business days prior to the Bid Submission Date | 03 Oct 2024 |
Bid Submission Date | 28 Nov 2024 |
Bidder’s Conference | 17 Dec 2023 |
Bid Registration and Notification: 20 (twenty) business days prior to the Bid Submission Date | 08 May 2024 |
Preferred Bidder announcement: Approximately 3 (three) months post the Bid Submission Date | |
Bid Submission: | 29 Aug 2024 |